Chilled and Frozen Distribution Hub

Chilled and Frozen Distribution Hub

As the first of its kind in the UK for a leading on-line retailer, Space Engineering were tasked with designing and installing the refrigeration equipment for a new £Multimillion, chilled and frozen facility.  As a turn-key project, we were assigned with the provision of the cold store construction, plant, controls, commissioning, and a supporting planned maintenance contract.

         

With a view on energy efficiency and future proofing of the refrigeration equipment, the best choice was a natural refrigerant – CO₂.

       

Working with the client on the expected room usage, we were able to calculate the heat loads.  This was then designed to a +35°c outside ambient, with 70% resilience between 2no refrigeration systems.  Each system has multiple compressors to share the running loads.  The Chilled design set point was at +1°c and the freezer design set point at -23°c.

        

To ensure energy efficiency we included parallel compressors, lead compressor inverters, EC fans, stepper expansion valves.

     

There was a restriction to the plant area footprint, so it was important to ensure the external equipment design was suitable.  For this reason, a V-block gas cooler was selected.

Environmental aspects had to be considered and overcome.  Noise levels were met, inverters were used for capacity control, future heat reclaim potential was included with a matrix of potential heat output to consider.

       

Some of the notable design elements of the project were:

  • Evaporator structural support design, split in pack/evaporator allocation to ensure full room operation in the event of a single plant failure
  • Fire strategy review with door positions worked through and established
  • Vertical evaporator pipework tails to limit condensation, EC fans, Freezer evaporator air socks and rear damper for the best possible defrost
  • Strategy of positioning Leak detection beacons/sounders and sensor locations to ensure persons and equipment were best protected
  • Shared containment co-ordination of refrigeration services with other discipline
  • Evaporator valve board drip trays included with connections to drain headers
  • Clear access locations and route highlighted above cold rooms for service and maintenance
  • Internal support with commissioning team providing a ‘commissioning intent’ document covering set points and operation of all equipment

         

Working to a short time scale and delivering the project during the COVID pandemic, Space delivered on time and on budget.

 

Related projects.

National Foodservice Distribution Centre

National Foodservice Distribution Centre

As part of a competitive tender process for a leading UK food service provider, Space Engineering were awarded the refrigeration package on a new RDC...

Read more
Multi Heat Pump Solution

Multi Heat Pump Solution

With our continued excellent working relationship with Mid Devon District Council, Space Engineering were awarded the contract to replace the gas boilers at Lords Meadow...

Read more
Flagship Food Hall HT/LT Refrigeration Systems

Flagship Food Hall HT/LT Refrigeration Systems

When one of the UK's leading retailers wanted to create 'one of their big five' food halls at a large out of town shopping centre...

Read more

Contact Us

We’d love to hear from you. Please enter your details in the form below and we will get back to you.

    I would like to opt in to marketing communications

    We take your privacy seriously. We will keep your data safe and we won’t pass it on to any third parties.
    Please see our privacy policy for more details.