De-carbonisation of Learning Centre

De-carbonisation of Learning Centre

Space Engineering were approached, by our client, to look at a scheme for Carmarthen County Council.  As part of the de-carbonisation process, the Learning Centre wanted to replace the existing boiler system with a heat pump system.

          

Our objective was to remove the existing gas supplies and gas fired boiler.  This included an existing single pipe heating system and radiators.

           

This enabled the team to install a new air to water heat pump, flow & return pipework and radiators.

           

We selected a Mitsubishi heat pump for the project.  Due to the fabric of the building, the equipment was sized on 80w/m2.  The CAHV-P500YB-HPB is capable of 43kw with a heating outlet of 60°c

         

The installation included new energy meters and a heat pump enclosure.

              

 

Related projects.

M&S Food Hall Refrigeration Replacement

M&S Food Hall Refrigeration Replacement

As part of a competitive tender process, Space Engineering successfully secured the multi phased upgrade works for an existing M&S retail site in Fosse Park....

Read more
Picking Freezer Refrigeration

Picking Freezer Refrigeration

Our valued customer needed to replace their high GWP refrigeration equipment for their picking freezer.  As Space Engineering understand our clients needs, factoring both CAPEX...

Read more
AHU & Chiller Installation

AHU & Chiller Installation

One of Europe's leading meat processors approached Space Engineering, to provide a ventilation solution, for one of their meat processing facilities in England. We were...

Read more

Contact Us

We’d love to hear from you. Please enter your details in the form below and we will get back to you.

    I would like to opt in to marketing communications

    We take your privacy seriously. We will keep your data safe and we won’t pass it on to any third parties.
    Please see our privacy policy for more details.